NKT is preferred supplier for Triton Knoll offshore wind farm project

Udgivet den 25-09-2017  |  kl. 06:45  |  

25 September 2017
Announcement No. 21

NKT is preferred supplier for Triton Knoll offshore wind farm project
NKT has signed a Preferred Supplier Agreement (PSA) for delivery and installation of export and array cable systems to the prospective offshore wind farm project Triton Knoll. The project is being developed as a joint venture by innogy (50%) and Statkraft (50%), with innogy managing the project. The PSA is signed in a consortium with Boskalis' subsidiary VBMS.

A PSA is a key step towards a final order which is conditional upon final negotiation of the EPC contract and the project owners, innogy and Statkraft, making a final investment decision for the offshore wind farm. That decision is expected Mid-2018.

The Triton Knoll project comprises the manufacture of approx. 100 km of 220 kV AC offshore export cables and approx. 144 km of 66 kV array cables as well as installation. The offshore wind farm is to be situated in the southern North Sea, off the UK east coast.

For NKT, the final order will have an estimated contract value of approx. EUR 115m (approx. DKK 857m) in market prices and it is subject to the above mentioned financial close. The cables will be delivered in Q4 2019 and Q2 2020, respectively.

NKT President and CEO Michael Hedegaard Lyng says:
- The recent allocation of contracts in the UK to build a number of new wind farms underlines our view that the offshore wind market remains attractive in the years to come. Obtaining the preferred supplier status for the Triton Knoll project shows that NKT is well positioned to take part in further growth and development of this market.

Triton Knoll was recently successful in the latest Contract for Difference (CfD) allocation round in the UK, and is targeted to be one of the most cost effective and low cost generating wind farm projects in the UK. Triton Knoll offshore wind farm is expected to begin commissioning in 2021 and will provide electricity for more than 800,000 households per annum, marking a key step in delivering UK renewable energy targets.

Contact
Investor Relations:    Michael Nass Nielsen, Head of Investor Relations, tel: +45 2494 1654
Media Relations:       Helle Gudiksen, Head of Group Communications, tel: +45 2349 9098

Vedhæftede filer:

NKT is preferred supplier for Triton Knoll offshore wind farm project_21 .pdf

Udgivet af: NPinvestordk

Seneste nyheder

17:48 Europa/aktier: Trodsede fransk regeringskrise og tunge danske aktiedrop
17:36 Tryg vil flekse muskler i ny strategiperiode med fokus på skala
17:18 Vestas dykker til laveste niveau siden corona: Investorer taber værdi på 12 mia. kr.
17:05 Onsdagens aktier: Tunge Mærsk, Vestas og Carlsberg trak i minus
17:00 Onsdagens obligationer: Meget rolig rente trods skuffende data fra USA
16:33 Amerikanske olielagre faldt langt mere end ventet i sidste uge
16:22 Mindre rente- og dollarfald efter skuffende amerikansk nøgletal
16:07 General Motors nedskriver 5 mia. dollar på sin problemramte kinesiske forretning
15:42 USA/åbning: Stimen ser ud til at fortsætte med årets 56. rekord i sigte
15:36 Direktør i USA's største sygekasse skudt på gaden i New York
15:22 ECB's Lagarde ser svagere økonomisk vækst og usikre udsigter
14:51 ADP-rapporten skuffede lidt i november: USA's arbejdsmarked er dog stadig i god gænge
14:12 USA/tendens: Sigter mod årets 56. rekord for S&P 500
13:26 Novo/Sydbank: Ikke den store overraskelse at Zepbound giver større vægttab end Wegovy
13:12 Coloplast frasælger kerneprodukter i hudplejeforretningen
13:06 Novo sættes til vægs af ærkerival: Wegovy giver mindst vægttab
12:57 Europa/aktier: Trodser fransk regeringskrise og holder lille plus
12:39 Kursfald i NKT giver attraktiv indgangsvinkel for den tålmodige investor mener Danske Bank
12:19 Trygs topchef: Konservatisme har gjort os godt i turbulent periode
12:11 Obligationer/middag: Fortsat dans på stedet